BAE Systems tracked 155mm self-propelled howitzer for the U.S. Army.

by BAE Systems

FieldedGround vehicleLandFirst deliveryApr 9, 2015
An M109A7 Paladin self-propelled howitzer firing during training in Poland

Photo: U.S. Army National Guard photo by Sgt. Gavin K. Ching · Public domain (PD-USGov-Military-Army) · Resized and reencoded as WebP; no additional crop or retouching. Credit retained for factual editorial product coverage.

Modernized Paladin self-propelled howitzer, paired with the M992A3 ammunition carrier, that BAE Systems builds for the U.S. Army.

Timeline1

  1. First deliveryConfirmed

    First LRIP M109A7 delivered to the Army

The latest 10 milestones. Solid entries are confirmed, outlined reported, dashed estimated or still to come; dotted italic entries are speculative. Dates show only the precision the sources give.

Operators1

  • USUnited States

Cost to the Government

Ground vehicles · BAE Systems

M109A7 Paladin / M992A3 PIM set

Compare platform costs →

The procurement denominator is a two-vehicle PIM set: one howitzer plus its tracked ammunition carrier.

Procurement / two-vehicle PIM set

$20.887M

FY2025 request · PB2025 · Nominal USD; budget-year program scope

Army budget: $417.741M / 20 sets, including support. Not the standalone M109A7 howitzer price.

U.S. Army ↗

U.S. inventory

Not verified

A current U.S. inventory was not established. Annual procurement, cumulative deliveries and production capacity are not a stockpile count.

PIM sets requested

20

FY2025 request · PB2025 · U.S. only; stated source scope

Each set includes M109A7 and M992A3; not 20 individual vehicles.

U.S. Army ↗

Program-specific annual RDT&E

$42.5M / yr

FY2025 · PB2025 historical budget snapshot · Nominal USD; source budget basis

Annual research appropriation/reference, not lifetime development cost. FY2025 figures in PB2025 are requests; PB2027 shows FY2025 actuals, FY2026 enacted/spend plan, FY2027 request.

DoD Comptroller ↗

A program objective is not current inventory

PB2025 describes a 689-set acquisition objective and sustainment through 2050. Those are historical planning assumptions, not a current fielded count.

Operations & sustainment

Annual operations & support

Not verified

A complete, system-specific annual operating and support cost was not established. Procurement, replacement rounds and contract support are different measures.

Cost over time · 6 observations

Each row retains its original scope and dollar basis. Changing quantities, service life and inflation can change the estimate without changing the price of building one unit.

M109A7 Paladin / M992A3 PIM set cost history
ObservationMeasureAmountDollar basisEvidence
FY2023 · PB2025 historical budget snapshotPIM annual procurement

Annual program funding in the cited budget vintage; not a unit price, contract award, or actual delivery count.

$1.009BNominal USD; source budget basisU.S. Army ↗
FY2024 · PB2025 historical budget snapshotPIM annual procurement

Annual program funding in the cited budget vintage; not a unit price, contract award, or actual delivery count.

$469.152MNominal USD; source budget basisU.S. Army ↗
FY2025 · PB2025 historical budget snapshotPIM annual procurement

Annual program funding in the cited budget vintage; not a unit price, contract award, or actual delivery count.

$417.741MNominal USD; source budget basisU.S. Army ↗
FY2023 · PB2025 historical budget snapshotProgram-specific annual RDT&E

Annual research appropriation/reference, not lifetime development cost. FY2025 figures in PB2025 are requests; PB2027 shows FY2025 actuals, FY2026 enacted/spend plan, FY2027 request.

$17.3M / yrNominal USD; source budget basisDoD Comptroller ↗
FY2024 · PB2025 historical budget snapshotProgram-specific annual RDT&E

Annual research appropriation/reference, not lifetime development cost. FY2025 figures in PB2025 are requests; PB2027 shows FY2025 actuals, FY2026 enacted/spend plan, FY2027 request.

$42.5M / yrNominal USD; source budget basisDoD Comptroller ↗
FY2025 · PB2025 historical budget snapshotProgram-specific annual RDT&E

Annual research appropriation/reference, not lifetime development cost. FY2025 figures in PB2025 are requests; PB2027 shows FY2025 actuals, FY2026 enacted/spend plan, FY2027 request.

$42.5M / yrNominal USD; source budget basisDoD Comptroller ↗
Contracts & purchasing · 1 records

Award values, ceilings and purchase agreements have different meanings. These records are not added together as total spending.

  • 2024-11-12 · Production award · market update

    U.S. Army → BAE Systems

    $493M · quantity not established

    Includes howitzers and ammunition carriers; quantity not disclosed in the cited announcement.

    BAE Systems ↗

International buyers

  • United States · 20 · U.S. procurement customer · Dated source snapshot

    Budget request, not evidence of deliveries or a current fleet inventory.

    DoD Comptroller ↗
Coverage & open research
  • Buyer records are selected examples, not a complete global order book.
  • Current U.S. inventory requires additional public evidence; procurement quantities are not inventory.
  • Complete system-specific annual operating and support costs were not established.

Unit costs and contract unit prices for this system, and budget figures for the programs that buy it. Each figure states its dollar basis and links its source; contract values are under Programs & awards.