M142 HIMARS
Compatible load: two PrSM rounds. Does not imply every legacy launcher has received all required updates.
Link Confirmed
Missile · Land
Surface-to-surface precision-strike missile for HIMARS and M270A2 launchers.
Army announces initial PrSM Increment 1 delivery
The Army announced initial delivery of Early Operational Capability missiles following November qualification testing. This is the announcement date; the handover date is unspecified.
Up to $4.94B production IDIQ
GAO assessment: PrSM testing and production progress
GAO’s June 2025 assessment covers the first two PrSM increments. The August 2024 estimate includes 4,021 missiles: 3,986 procurement and 35 development. The Army reported 26 early operational missiles delivered as of January 2025. Initial operational capability for Increment 1 remained a fiscal 2026 target; GAO reported manufacturing-related schedule delays. See report pp. 111–112.
First combat use (Increment 1)
The Army first used PrSM Increment 1 in combat in March 2026 during the conflict with Iran.
$8.4B production modification through FY2032
Increment 2 early operational capability contract
The latest 10 milestones. Solid entries are confirmed, outlined reported, dashed estimated or still to come; dotted italic entries are speculative. Dates show only the precision the sources give.
Missiles · Lockheed Martin
Baseline recurring-production estimates and a production-contract ceiling, with future deliveries kept separate from fielded inventory.
Baseline recurring production / missile
$1.622M
FY2026 request · Nominal USD; source budget basis
P-5 C29850 PrSM Baseline recurring-production line. Excludes other increments and program support; nominal budget estimate, not the price of a complete launcher.
U.S. Army ↗U.S. inventory
Not verified
A current U.S. inventory was not established. Annual procurement, cumulative deliveries and production capacity are not a stockpile count.
Baseline missile purchase request
35
FY2026 · U.S. only; stated source scope
C29850 baseline subprogram only; excludes other PrSM increments. P-5a anticipated first delivery in March 2029, not fielding in FY2026.
U.S. Army ↗Annual RDT&E funding
$184M / yr
FY2025 · FY2025 budget book · Nominal USD; source budget basis
Missiles & Munitions · PrSM. Annual research, development, test and evaluation funding in the March 2024 budget presentation; FY2024 and FY2025 are request figures. Not a lifetime R&D total or actual expenditure.
DoD Comptroller ↗Baseline gross procurement request
$65.582M
FY2026 · Nominal USD; source budget basis
Baseline subprogram total includes support beyond recurring production.
U.S. Army ↗The budget records a baseline production quantity and separate program work. The requested purchase year precedes planned deliveries; neither establishes the current operational stockpile.
Annual operations & support
Not verified
A complete, system-specific annual operating and support cost was not established. Procurement, replacement rounds and contract support are different measures.
Each row retains its original scope and dollar basis. Changing quantities, service life and inflation can change the estimate without changing the price of building one unit.
| Observation | Measure | Amount | Dollar basis | Evidence |
|---|---|---|---|---|
| FY2025 · PB2026 estimate | Baseline recurring production / missile P-5 C29850 PrSM Baseline recurring-production line. Excludes other increments and program support; nominal budget estimate, not the price of a complete launcher. | $1.611M | Nominal USD; source budget basis | U.S. Army ↗ |
| FY2026 request | Baseline recurring production / missile P-5 C29850 PrSM Baseline recurring-production line. Excludes other increments and program support; nominal budget estimate, not the price of a complete launcher. | $1.622M | Nominal USD; source budget basis | U.S. Army ↗ |
| FY2023 · FY2025 budget book | Annual RDT&E funding Missiles & Munitions · PrSM. Annual research, development, test and evaluation funding in the March 2024 budget presentation; FY2024 and FY2025 are request figures. Not a lifetime R&D total or actual expenditure. | $250M / yr | Nominal USD; source budget basis | DoD Comptroller ↗ |
| FY2024 · FY2025 budget book | Annual RDT&E funding Missiles & Munitions · PrSM. Annual research, development, test and evaluation funding in the March 2024 budget presentation; FY2024 and FY2025 are request figures. Not a lifetime R&D total or actual expenditure. | $272.8M / yr | Nominal USD; source budget basis | DoD Comptroller ↗ |
| FY2025 · FY2025 budget book | Annual RDT&E funding Missiles & Munitions · PrSM. Annual research, development, test and evaluation funding in the March 2024 budget presentation; FY2024 and FY2025 are request figures. Not a lifetime R&D total or actual expenditure. | $184M / yr | Nominal USD; source budget basis | DoD Comptroller ↗ |
Award values, ceilings and purchase agreements have different meanings. These records are not added together as total spending.
2025-03-31 · IDIQ ceiling
U.S. Army → Lockheed Martin
$4.94B · quantity not established
Ordering capacity, not obligations or a fixed quantity. The announcement does not establish a per-round price.
Lockheed Martin ↗Launcher and munition
M270A2 Multiple Launch Rocket System
M270 family compatibility; configuration and modernization requirements vary by munition.
Lockheed Martin ↗No international purchase documented in this review.
Army procurement only (P-40 'Total' column: prior years through FY2031, 3,550 missiles, $7,025.122M gross weapon system cost); excludes RDT&E. FY2027 budget books.
GAO-25-107569 printed p. 111 (PDF p. 121); estimate dated 2024-08, expressed in constant FY2025 dollars. Visually transcribed from the program performance graphic, whose amounts are in millions. Historical estimate, not a current price or contract award. Total covers development and procurement quantities.
FY 2027 request, P-5 PrSM Baseline (Increment 1) recurring production unit cost $1,551.131K for 664 missiles (FY2025 $1,343.118K for 338; FY2026 $1,725.417K for 108). PrSM Increment 2 FY2027: $5,170.563K for 16.
GAO-25-107569 printed p. 111 (PDF p. 121); estimate dated 2024-08, expressed in constant FY2025 dollars. Visually transcribed from the program performance graphic, whose amounts are in millions. Historical estimate, not a current price or contract award. Program acquisition unit cost (PAUC); GAO methodology p. 197 divides program cost by total quantities. Report-rounded value, not flyaway or procurement unit price.
| Fiscal year | Appropriation | Request | Enacted | Qty | Budget line | Source |
|---|---|---|---|---|---|---|
| FY2027 | RDT&E | $288M | — | — | — | SourceConfirmed |
| FY2027 | Procurement | $1.93B | — | 1,134 | — | SourceConfirmed |
| FY2027 | Total | $2.22B | — | 1,134 | — | SourceConfirmed |
| FY2026 | RDT&E | $197M | $197M | — | — | SourceConfirmed |
| FY2026 | Procurement | $364M | $547M | 108 | — | SourceConfirmed |
| FY2026 | Total | $561M | $744M | 108 | — | SourceConfirmed |
| FY2025 | RDT&E | — | $184M | — | — | SourceConfirmed |
| FY2025 | Procurement | — | $458M | 230 | — | SourceConfirmed |
| FY2025 | Total | — | $642M | 230 | — | SourceConfirmed |
Unit costs and contract unit prices for this system, and budget figures for the programs that buy it. Each figure states its dollar basis and links its source; contract values are under Programs & awards.

Compatible load: two PrSM rounds. Does not imply every legacy launcher has received all required updates.
Link Confirmed