Skip to content
DefDex

Interceptor · Sea

Standard Missile 6 (SM-6)

Extended-range naval air defense missile with additional surface and missile-defense roles.

by RTX · First fielded 2013

FieldedInterceptorSeaContract awardOct 1, 2026
  • Milestones2
  • Operators—
  • Components—
  • Programs—
  • Capabilities—
  • Inputs—

Timeline2

  1. Initial operating capabilityConfirmed

    SM-6 achieves initial operational capability

  2. Contract awardConfirmed

    Five-year multi-year procurement contract (up to $24.4B)

The latest 10 milestones. Solid entries are confirmed, outlined reported, dashed estimated or still to come; dotted italic entries are speculative. Dates show only the precision the sources give.

In Service

First fielded
2013

Cost to the Government

Missiles · RTX / Raytheon

Standard Missile-6 (SM-6)

Compare platform costs →

A budget-derived Block IA procurement average is shown alongside annual R&D and the new multiyear production agreement.

Derived procurement funding / missile

$6.042M

FY2025 request · March 2024 · Nominal USD; source budget basis

Calculation: $755.2M procurement / 125 missiles. Funding includes missiles and canisters; this is not a recurring flyaway quote.

DoD Comptroller ↗

U.S. inventory

Not verified

A current U.S. inventory was not established. Annual procurement, cumulative deliveries and production capacity are not a stockpile count.

Block IA requested missiles

125

FY2025 request · U.S. only; stated source scope

Procurement quantity in the March 2024 budget book; not delivered inventory.

DoD Comptroller ↗

Annual RDT&E funding

$468.3M / yr

FY2025 · FY2025 budget book · Nominal USD; source budget basis

Missiles & Munitions 5-17. Annual research, development, test and evaluation funding in the March 2024 budget presentation; FY2024 and FY2025 are request figures. Not a lifetime R&D total or actual expenditure.

DoD Comptroller ↗

Development and production cover different variants

The FY2025 procurement request buys Block IA rounds while development funding supports Block IB and other improvements. Annual R&D therefore is not an extra charge on each Block IA round.

Operations & sustainment

Annual operations & support

Not verified

A complete, system-specific annual operating and support cost was not established. Procurement, replacement rounds and contract support are different measures.

Cost over time · 6 observations

Each row retains its original scope and dollar basis. Changing quantities, service life and inflation can change the estimate without changing the price of building one unit.

Standard Missile-6 (SM-6) cost history
ObservationMeasureAmountDollar basisEvidence
FY2023 · FY2025 budget bookAnnual SM-6 procurement funding

Funding scope includes procurement support; FY2024 and FY2025 are request figures. Do not read changes as standalone hardware-price inflation.

$489.1MNominal USD; source budget basisDoD Comptroller ↗
FY2024 · FY2025 budget bookAnnual SM-6 procurement funding

Funding scope includes procurement support; FY2024 and FY2025 are request figures. Do not read changes as standalone hardware-price inflation.

$1.197BNominal USD; source budget basisDoD Comptroller ↗
FY2025 · FY2025 budget bookAnnual SM-6 procurement funding

Funding scope includes procurement support; FY2024 and FY2025 are request figures. Do not read changes as standalone hardware-price inflation.

$755.2MNominal USD; source budget basisDoD Comptroller ↗
FY2023 · FY2025 budget bookAnnual RDT&E funding

Missiles & Munitions 5-17. Annual research, development, test and evaluation funding in the March 2024 budget presentation; FY2024 and FY2025 are request figures. Not a lifetime R&D total or actual expenditure.

$298.3M / yrNominal USD; source budget basisDoD Comptroller ↗
FY2024 · FY2025 budget bookAnnual RDT&E funding

Missiles & Munitions 5-17. Annual research, development, test and evaluation funding in the March 2024 budget presentation; FY2024 and FY2025 are request figures. Not a lifetime R&D total or actual expenditure.

$418.2M / yrNominal USD; source budget basisDoD Comptroller ↗
FY2025 · FY2025 budget bookAnnual RDT&E funding

Missiles & Munitions 5-17. Annual research, development, test and evaluation funding in the March 2024 budget presentation; FY2024 and FY2025 are request figures. Not a lifetime R&D total or actual expenditure.

$468.3M / yrNominal USD; source budget basisDoD Comptroller ↗
Contracts & purchasing · 1 records

Award values, ceilings and purchase agreements have different meanings. These records are not added together as total spending.

  • 2026-10-01 · Maximum multiyear contract value

    U.S. government / Navy → RTX / Raytheon

    $24.4B · quantity not established

    Five years plus two option years. Announced upper value is not current obligations; quantity not disclosed.

    RTX ↗

Connected missiles & systems

  • Ground launch system and missile

    Typhon / Mid-Range Capability

    Army MRC combines these missile families with ground launch and control equipment.

    U.S. Army ↗
  • Naval launcher and missile

    Mk 41 Vertical Launching System →

    Listed Mk 41 missile family; support depends on launcher configuration and ship combat-system integration.

    Lockheed Martin ↗

International buyers

No international purchase documented in this review.

Coverage & open research
  • Current U.S. inventory and complete annual operating-and-support costs require additional public evidence.
  • Buyer records are selected examples, not a complete global order book.
  • The displayed R&D reference is annual funding or a specified multi-year request window, not a verified lifetime total.
  • Additional primary-source international purchase and delivery records remain to be reviewed.
  • Unit cost (per round)Reported
    $4.3M
    Estimate / observation: 2024-05-21 · Then-year $

    The War Zone (May 2024), based on Pentagon budget documents of the prior five years, rounded to nearest $10,000: SM-6 $4.27M per round.

    Source
Earlier cost observations (2)
  • Standard Missile 6 (SM-6) · Unit cost (per round) · $4.3M
    Estimate / observation: 2020-12-11 · Then-year $ · FY2021

    FY2021 Navy budget request average unit price for SM-6 (Block I and Block IA) as reported by The War Zone from official budget documents.

    Source
  • Standard Missile 6 (SM-6) · Unit cost (per round) · $5.5M
    Then-year $ · 14 units

    Army Mid-Range Capability SM-6 Block IA buy, FY 2027 request P-5: $5,497.643K per missile for 14 (FY2026 $5,448.667K for 6). Navy WPN book not machine-fetchable.

    Source
Budget by fiscal year
Fiscal yearAppropriationRequestEnactedQtyBudget lineSource
FY2027RDT&E$539M———SourceConfirmed
FY2027Procurement$4.33B—540—SourceConfirmed
FY2027Total$4.87B—540—SourceConfirmed
FY2026RDT&E$413M$512M——SourceConfirmed
FY2026Procurement$850M$1.41B166—SourceConfirmed
FY2026Total$1.26B$1.92B166—SourceConfirmed
FY2025RDT&E—$288M——SourceConfirmed
FY2025Procurement—$694M78—SourceConfirmed
FY2025Total—$983M78—SourceConfirmed

Unit costs and contract unit prices for this system, and budget figures for the programs that buy it. Each figure states its dollar basis and links its source; contract values are under Programs & awards.