Federal award
JIMMY CLOSNER & SONS CONSTRUCTION CO., INC.
0002
Contract
Obligated and Ceiling
- Obligated (net)
- $2,933,918.09
- Ceiling (potential value, not spending)
- $2,933,918.09
- Current value
- $2,933,918.09
- Gross positive obligations
- $2,962,061.42
Obligated is what the government has committed, net of de-obligations. The ceiling is the most the award or vehicle could ever reach; it is shown separately and never added to, or compared as, spending.
Award Details
- Recipient
- JIMMY CLOSNER & SONS CONSTRUCTION CO., INC. · ZARPSUZSLMJ8
- Owner company
- Not a reviewed companyNo reviewed company owns this recipient.
- Reported parent
- JIMMY CLOSNER & SONS CONSTRUCTION CO., INC. · ZARPSUZSLMJ8
- Awarding agency
- Department of War · sub-agency 2100 · office W912HY
- Funding agency
- Department of War · sub-agency 2100
- Product or service (PSC)
- Z166
- Industry (NAICS)
- 237990 · OTHER HEAVY AND CIVIL ENGINEERING CONSTRUCTION
- PIID
- 0002
- Parent vehicle (IDV PIID)
- W912HY08D0004
- Award type code
- C
- Actions
- 14 · Aug 6, 2008 to Mar 4, 2010
- Why it is listed
- gross positive obligations of $100k or more (contracts)
Action History14
| Date | FY | Mod | Action type | Obligation | Company in company totals |
|---|---|---|---|---|---|
| Mar 4, 2010 | FY2010 | 13 | K | −$28,143.33 | — |
| May 2, 2009 | FY2009 | 12 | D | $7,453.00 | — |
| Feb 26, 2009 | FY2009 | 11 | D | $43,321.00 | — |
| Feb 25, 2009 | FY2009 | 10 | D | $91,945.00 | — |
| Feb 24, 2009 | FY2009 | 9 | D | $35,720.00 | — |
| Feb 19, 2009 | FY2009 | 8 | D | $41,550.00 | — |
| Feb 19, 2009 | FY2009 | 7 | L | $5,650.00 | — |
| Dec 2, 2008 | FY2009 | 5 | D | $95,896.52 | — |
| Dec 2, 2008 | FY2009 | 6 | D | $91,510.00 | — |
| Sep 29, 2008 | FY2008 | 4 | D | $134,685.00 | — |
| Sep 8, 2008 | FY2008 | 3 | L | $986,571.72 | — |
| Sep 6, 2008 | FY2008 | 2 | L | $332,759.18 | — |
| Aug 19, 2008 | FY2008 | 1 | C | $495,000.00 | — |
| Aug 6, 2008 | FY2008 | 0 | — | $600,000.00 | — |
Newest first. Every obligation is shown as reported, including zero and negative (de-obligation) actions. Award lists belong to the company of the latest action; company totals credit each action to the company named on that row, so a note marks rows where the two differ.