System · Undersea
Orca XLUUV
Boeing extra-large unmanned undersea vehicle for U.S. Navy mine laying, derived from Echo Voyager; five vehicles ordered.
by Boeing
- Milestones2
- Operators1
- Components—
- Programs—
- Capabilities1
- Inputs—
Boeing extra-large unmanned undersea vehicle for U.S. Navy mine laying, derived from Echo Voyager; five vehicles ordered.
Timeline2
- First deliveryReported
First Orca delivered to the U.S. Navy
- MilestoneConfirmed
GAO assessment: Orca prototype delays and technology risks
GAO’s June 2025 assessment describes Orca as a research and development effort. The Navy received a test asset in December 2023 and, as of January 2025, expected five prototypes by the end of 2025. GAO identified fabrication, battery, autonomy and navigation challenges. Procurement costs and quantities for a possible program of record were undetermined; the delivery expectation is not evidence of completed deliveries.
The latest 10 milestones. Solid entries are confirmed, outlined reported, dashed estimated or still to come; dotted italic entries are speculative. Dates show only the precision the sources give.
Operators1
- USUnited States
Cost to the Government
- Total acquisition costConfirmed$621MThen-year $ · 5 units
GAO-22-105974 (Sep 2022), based on the FY2023 President's Budget: $621M planned to build five XLUUVs incl. a $73M test vehicle; original 2016 estimate $379M (64% growth).
Source - Contract unit priceEstimated$10.8M4 units
Feb 2019 Navy contract modification to Boeing: $43M for fabrication, test and delivery of four Orca XLUUVs and support elements; $43,000,000 / 4 = $10.75M per vehicle (division by us). GAO later put the cost of five vehicles at $621M.
Source
Unit costs and contract unit prices for this system, and budget figures for the programs that buy it. Each figure states its dollar basis and links its source; contract values are under Programs & awards.