Budget tracker
Next-Generation OPIR GEO
Space Force R-1 program element 1206443SF, Next-Gen OPIR -- GEO. Discretionary and mandatory are separate figures. Total columns are not stored. FY2027 enacted line amounts are not loaded: P.L. 119-103 states no program-line amount. Obligations are the published award whose title names Next-Gen OPIR GEO. Announced ceilings are not included.
By Fiscal Year
FY2025
- Requested
- —
- Enacted
- $459M$458,727,000
Appropriation
- RDT&E · 1206443SF · Appropriation · $459M
- Announced ceiling (not spending)
- —
- Obligated
- No actions recorded on published linked awards
FY2026
- Requested
- $432M$432,073,000
President's budget
- RDT&E · 1206443SF · Discretionary · President's budget · $432M
- Enacted
- $422M$422,173,000
Appropriation
- RDT&E · 1206443SF · Discretionary · Appropriation · $422M
- Announced ceiling (not spending)
- —
- Obligated
- $3.1M$3,115,738
1 linked award, 1 action · partial year
FY2027
- Requested
- $486M$485,703,000
President's budget
- RDT&E · 1206443SF · Discretionary · President's budget · $486M
- Enacted
- —
- Announced ceiling (not spending)
- —
- Obligated
- No actions recorded on published linked awards yet
Each column is a different measure and they are not added together. A request and an enacted amount for the same year sit side by side; the request is never rewritten when an enacted amount arrives. A blank state names why there is no amount; only a stated amount, including a stated $0, shows dollars.
Sources and Evidence4
FY2025 · Enacted (Appropriation)
RDT&E · 1206443SF
$458,727,000as printed 458,727 ($ thousands)FY 2026 Research, Development, Test & Evaluation Programs (R-1) Office of the Under Secretary of Defense (Comptroller) · document Jun 26, 2025FY2026 President's Budget (Jun 2025), column FY 2025 EnactedExhibit R-1, PDF page 60, line 34 1206443SF Next-Gen OPIR -- GEO. Dollars in thousands. Column 'FY 2025 Enacted'.34 1206443SF Next-Gen OPIR -- GEO 05 U 691,069 458,727 458,727 432,073 432,073
The exhibit total column is not stored. Discretionary and mandatory are separate figures.FY2026 · Requested (President's budget)
RDT&E · 1206443SF · Discretionary
$432,073,000as printed 432,073 ($ thousands)FY 2026 Research, Development, Test & Evaluation Programs (R-1) Office of the Under Secretary of Defense (Comptroller) · document Jun 26, 2025FY2026 President's Budget (Jun 2025), column FY 2026 Disc RequestExhibit R-1, PDF page 60, line 34 1206443SF Next-Gen OPIR -- GEO. Dollars in thousands. Column 'FY 2026 Disc Request'.34 1206443SF Next-Gen OPIR -- GEO 05 U 691,069 458,727 458,727 432,073 432,073
The exhibit total column is not stored. Discretionary and mandatory are separate figures.FY2026 · Enacted (Appropriation)
RDT&E · 1206443SF · Discretionary
$422,173,000as printed 422,173 ($ thousands)RDT&E Programs (R-1), Department of War Budget, Fiscal Year 2027 Office of the Under Secretary of War (Comptroller) · document Apr 21, 2026FY2027 President's Budget (Apr 2026), column FY 2026 Discretionary EnactedExhibit R-1, PDF page 60, line 32 1206443SF Next-Gen OPIR -- GEO. Dollars in thousands. Column 'FY 2026 Discretionary Enacted'.32 1206443SF Next-Gen OPIR -- GEO 05 U 458,727 422,173 422,173 485,703 485,703
The exhibit total column is not stored. Discretionary and mandatory are separate figures.FY2027 · Requested (President's budget)
RDT&E · 1206443SF · Discretionary
$485,703,000as printed 485,703 ($ thousands)RDT&E Programs (R-1), Department of War Budget, Fiscal Year 2027 Office of the Under Secretary of War (Comptroller) · document Apr 21, 2026FY2027 President's Budget (Apr 2026), column FY 2027 Discretionary RequestExhibit R-1, PDF page 60, line 32 1206443SF Next-Gen OPIR -- GEO. Dollars in thousands. Column 'FY 2027 Discretionary Request'.32 1206443SF Next-Gen OPIR -- GEO 05 U 458,727 422,173 422,173 485,703 485,703
The exhibit total column is not stored. Discretionary and mandatory are separate figures.
Every figure keeps its document, date, page or table, original unit and a short excerpt. Superseded figures stay on record. Amounts are exact; compact figures round.
Linked Awards1
- NEXT-GEN OPIR GEO (NGG) GAP ANALYSIS
CONT_AWD_FA857926C0009_9700_-NONE-_-NONE-
LOCKHEED MARTIN CORP · Award title or description names the program
NEXT-GEN OPIR GEO (NGG) GAP ANALYSIS
- FY2026: $3,115,738
USAspending awards reviewed as belonging to this program, matched on the exact award key, never on a similar name. Some are linked only because the DoW acquisition program code reported on the award maps to this program; that code is the agency's own field and can be wrong, so those rows are labelled separately. Net obligations through Oct 6, 2026; later years are partial. The appropriation that paid for an award is not identified, so obligations are not compared with the enacted column.
Method
Four measures
- Requested
- What a budget request asked for. Not money Congress provided.
- Enacted
- What a law provided, or a spend plan's allocation of a law's lump sum.
- Announced ceiling
- The most a contract vehicle or agreement could be worth, as announced. Not spending.
- Obligated
- Net obligations on USAspending actions of the awards linked to the program. The funding account is not identified.
An announced ceiling is not spending
Figures come from the budget justification books, public laws and agency announcements named in the evidence table; where a source shows no amount the tracker says so rather than showing zero, and where DefDex has not yet checked a source it says that too. See the methodology for how federal obligations are counted.