Skip to content
DefDex

Program · United States · U.S. Space Force

Next-Generation OPIR GEO

Lockheed Martin geosynchronous missile-warning satellite for the U.S. Space Force.

Updated
DevelopmentU.S. Space Force
Awarded
—
Across linked awards

Timeline1

  1. MilestoneConfirmed

    First satellite completes environmental testing

    Lockheed Martin said on 6 August 2025 that the first satellite had completed environmental testing, including thermal vacuum testing; the completion date is not stated.

Program and variant milestones. Dates show only the precision the sources give.

Cost to the Government

Program totals · 3

  • Annual RDT&E fundingR-1 PE1206443SF Next-Gen OPIR GEO. Annual appropriation, not lifetime development. FY2026 includes listed reconciliation spend-plan funds; FY2027 is requested funding. Not a contract award or recurring hardware price.
    FY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2027 total request · PB2027
    $485.703M / yrNominal $; source budget basis
  • Historical five-year Next Gen OPIR development planBroader program, including satellites and ground systems; not GEO-only lifetime development or actual expenditure. GAO describes a five-year spending plan.
    Next Gen OPIR cost and schedule oversight, September 2021 Government Accountability Office · figure September 2021 GAO report
    $14.4BSource-reported $ · historical development plan
  • Next Gen OPIR ground annual RDT&E requestPE1206440SF ground segment, separate from GEO spacecraft development and not added to the GEO unit cost.
    FY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2027
    $761.425M / yrNominal $; source budget basis

Unit costs · 1

  • Comparable unit priceNo comparable standalone unit price was established; package or contract totals are shown separately.
    Source not recorded
    Not established

Quantities · 3

  • Broader Next Gen OPIR architectureCombined GEO and HEO/Polar satellites in GAO’s architecture table. Not four GEO spacecraft, delivered satellites, or a new order.
    Missile warning satellites: delivery risks and cost transparency, January 2026 Government Accountability Office · figure January 2026 GAO snapshot
    4U.S. only; stated source scope
  • U.S. inventoryA current U.S. inventory was not established. Annual procurement, cumulative deliveries and production capacity are not a stockpile count.
    Source not recorded
    Not established
  • U.S. procurement quantityNo comparable U.S. procurement quantity was established in this review.
    Source not recorded
    Not established

Operating costs · 1

  • Annual operations & supportA complete, system-specific annual operating and support cost was not established. Procurement, replacement rounds and contract support are different measures.
    Source not recorded
    Not established
Earlier observations · 3

Superseded estimates and prices, each in its original scope and dollar basis.

1R-1 PE1206443SF Next-Gen OPIR GEO. Annual appropriation, not lifetime development. FY2026 includes listed reconciliation spend-plan funds; FY2027 is requested funding. Not a contract award or recurring hardware price.

GEO design-review milestone

Space Systems Command documented the GEO critical design review on August 24, 2021 and identified Lockheed Martin as prime contractor. This milestone is not a procurement award or a current inventory count.

A constellation budget is not a spacecraft price

The GEO, Polar and ground programs have separate funding lines. The 2021 five-year development plan and 2026 four-satellite architecture snapshot have different dates and scopes; neither is divided into a current recurring GEO satellite price.

Next Gen OPIR cost and schedule oversight, September 2021 Government Accountability Office · +2 more
International buyers · 1
International buyers
CountryQtyStatusSource
United StatesGEO-specific funding, with broader constellation figures identified separately.Not verifiedSpace Force development programFY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2027 request

Open research: Current U.S. inventory and complete annual operating-and-support costs require additional public evidence. Buyer records are selected examples, not a complete global order book.

What the government budgets and pays for this program, from budget justification books, appropriations, acquisition reports and contract announcements. Each figure states its dollar basis. What contractors were obligated is under Contracts.