Skip to content
DefDex

Budget tracker

Next-Gen OPIR -- Polar

Space Force R-1 program element 1206444SF, Next-Gen OPIR -- Polar. The FY2026 request on this line is the reconciliation column only. The FY2027 request columns are blank, so FY2027 requested is empty. Discretionary enacted and mandatory request are separate figures. Total columns are not stored. FY2027 enacted line amounts are not loaded: P.L. 119-103 states no program-line amount. No published award title names this line. Announced ceilings are not included.

Source evidence reviewed Oct 23, 2026 · Program profile

By Fiscal Year

  • FY2025

    Requested
    —
    Enacted
    $769M$769,478,000

    Appropriation

    • RDT&E · 1206444SF · Appropriation · $769M
    Announced ceiling (not spending)
    —
    Obligated
    No awards linked yet
  • FY2026

    Requested
    $724M$723,700,000

    President's budget

    • RDT&E · 1206444SF · Mandatory · President's budget · $724M
    Enacted
    $437M$436,521,000

    Appropriation

    • RDT&E · 1206444SF · Discretionary · Appropriation · $437M
    Announced ceiling (not spending)
    —
    Obligated
    No awards linked yet
  • FY2027

    Requested
    —
    Enacted
    —
    Announced ceiling (not spending)
    —
    Obligated
    No awards linked yet

Each column is a different measure and they are not added together. A request and an enacted amount for the same year sit side by side; the request is never rewritten when an enacted amount arrives. A blank state names why there is no amount; only a stated amount, including a stated $0, shows dollars.

Sources and Evidence3

  • FY2025 · Enacted (Appropriation)

    RDT&E · 1206444SF

    $769,478,000as printed 769,478 ($ thousands)
    FY 2026 Research, Development, Test & Evaluation Programs (R-1) Office of the Under Secretary of Defense (Comptroller) · document Jun 26, 2025FY2026 President's Budget (Jun 2025), column FY 2025 Enacted
    Exhibit R-1, PDF page 60, line 35 1206444SF Next-Gen OPIR -- Polar. Dollars in thousands. Column 'FY 2025 Enacted'.35 1206444SF Next-Gen OPIR -- Polar 05 U 866,813 769,478 769,478 723,700 723,700The exhibit total column is not stored. Discretionary and mandatory are separate figures.
  • FY2026 · Requested (President's budget)

    RDT&E · 1206444SF · Mandatory

    $723,700,000as printed 723,700 ($ thousands)
    FY 2026 Research, Development, Test & Evaluation Programs (R-1) Office of the Under Secretary of Defense (Comptroller) · document Jun 26, 2025FY2026 President's Budget (Jun 2025), column FY 2026 Reconciliation Request
    Exhibit R-1, PDF page 60, line 35 1206444SF Next-Gen OPIR -- Polar. Dollars in thousands. Column 'FY 2026 Reconciliation Request'.35 1206444SF Next-Gen OPIR -- Polar 05 U 866,813 769,478 769,478 723,700 723,700The exhibit total column is not stored. Discretionary and mandatory are separate figures.
  • FY2026 · Enacted (Appropriation)

    RDT&E · 1206444SF · Discretionary

    $436,521,000as printed 436,521 ($ thousands)
    RDT&E Programs (R-1), Department of War Budget, Fiscal Year 2027 Office of the Under Secretary of War (Comptroller) · document Apr 21, 2026FY2027 President's Budget (Apr 2026), column FY 2026 Discretionary Enacted
    Exhibit R-1, PDF page 60, line 33 1206444SF Next-Gen OPIR -- Polar. Dollars in thousands. Column 'FY 2026 Discretionary Enacted'.33 1206444SF Next-Gen OPIR -- Polar 05 U 769,478 436,521 436,521The exhibit total column is not stored. Discretionary and mandatory are separate figures.

Every figure keeps its document, date, page or table, original unit and a short excerpt. Superseded figures stay on record. Amounts are exact; compact figures round.

Linked Awards

No awards are linked to this program yet.

USAspending awards reviewed as belonging to this program, matched on the exact award key, never on a similar name. Some are linked only because the DoW acquisition program code reported on the award maps to this program; that code is the agency's own field and can be wrong, so those rows are labelled separately. Net obligations through Oct 6, 2026; later years are partial. The appropriation that paid for an award is not identified, so obligations are not compared with the enacted column.

Method

Four measures

Requested
What a budget request asked for. Not money Congress provided.
Enacted
What a law provided, or a spend plan's allocation of a law's lump sum.
Announced ceiling
The most a contract vehicle or agreement could be worth, as announced. Not spending.
Obligated
Net obligations on USAspending actions of the awards linked to the program. The funding account is not identified.

An announced ceiling is not spending

A contract vehicle's ceiling can go unused, and the ceilings of multiple-award vehicles overlap in purpose. DefDex lists each announced ceiling separately and does not add ceilings together or to requested, enacted or obligated dollars.

Figures come from the budget justification books, public laws and agency announcements named in the evidence table; where a source shows no amount the tracker says so rather than showing zero, and where DefDex has not yet checked a source it says that too. See the methodology for how federal obligations are counted.