The profile’s obligated figure counts resolved program awards from reported acquisition codes and reviewed links, with shared awards excluded; the tracker counts catalog fiscal years of resolved reviewed award links, so the figures can differ. The budget tracker separates requested, enacted, announced ceiling and obligated amounts for FY2025–FY2027: LGM-35A Sentinel figures cover R-1 program element 0605238F and P-1 line 3020 Ground Based Strategic Deterrent. The exhibit titles say Ground Based Strategic Deterrent. They are included because the Air Force Global Strike Command fact sheet states that the LGM-35A Sentinel was originally called the Ground Based Strategic Deterrent, or GBSD. Parenthetical gross amounts and rows with no printed net are not included. Obligations are only the USAspending awards carrying reviewed DoW acquisition program code 493 (LGM-35A SENTINEL). Awards are not linked by a similar name. FY2027 enacted line amounts are not loaded: P.L. 119-103 states no program-line amount. Announced ceilings are not included.
About
The LGM-35A Sentinel program develops the Air Force's replacement for the Minuteman III intercontinental ballistic missile system. Its scope includes the missile, command-and-control and ground systems, and launch infrastructure supporting the land-based nuclear deterrent. Following a January 2024 critical unit-cost breach, the department required restructuring; GAO's June 2025 assessment described continuing design and acquisition reassessment.
News2
Cost to the Government
| Measure | Amount | Source |
|---|---|---|
| Totals · 3 | ||
| Total acquisition costCAPE reassessment scenario for a reasonably modified Sentinel program with redesigned launch facilities: about $170.6B in constant FY2025 dollars, about 81% above the September 2020 estimate. Not an approved new baseline or the program-performance chart estimate. Observation date is GAO report publication; the paragraph does not provide an exact date for the underlying CAPE estimate. GAO-25-107569 printed p. 80 (PDF p. 90). | $170.6BBY2025 $ | Weapon Systems Annual Assessment 2025 — LGM-35A Sentinel, p. 80 U.S. Government Accountability Office · Jun 11, 2025 |
| Annual RDT&E fundingR-1 PE0605238F Ground Based Strategic Deterrent EMD. Annual appropriation, not lifetime development. FY2026 includes listed reconciliation spend-plan funds; FY2027 is requested funding. Not a contract award or recurring hardware price. | $4.521B / yrNominal $; source budget basis | FY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2027 total request · PB2027 |
| CAPE program acquisition estimateSource-reported acquisition estimate for a reasonably modified program, including command/launch infrastructure. GAO in February 2026 says costs remain uncertain. Not lifetime operations cost or missile-only procurement. | $140.9BSource-reported $ · dollar year not specified in release | Sentinel Nunn-McCurdy review results, July 2024 U.S. Air Force · figure July 2024 restructuring review |
| Unit costs · 1 | ||
| Comparable unit priceNo comparable standalone unit price was established; package or contract totals are shown separately. | Not established | — |
| Quantities · 2 | ||
| Operational missiles to replaceReplacement mission for 400 Minuteman III missiles and 450 silos; not a total production quantity, new order or Sentinel inventory. | 400U.S. only; stated source scope | FY2027 Budget Request Overview, nuclear modernization and missile warning DoD Comptroller · figure FY2027 overview |
| U.S. inventoryA current U.S. inventory was not established. Annual procurement, cumulative deliveries and production capacity are not a stockpile count. | Not established | — |
| Operating costs · 1 | ||
| Annual operations & supportA complete, system-specific annual operating and support cost was not established. Procurement, replacement rounds and contract support are different measures. | Not established | — |
Totals · 3
- Total acquisition costCAPE reassessment scenario for a reasonably modified Sentinel program with redesigned launch facilities: about $170.6B in constant FY2025 dollars, about 81% above the September 2020 estimate. Not an approved new baseline or the program-performance chart estimate. Observation date is GAO report publication; the paragraph does not provide an exact date for the underlying CAPE estimate. GAO-25-107569 printed p. 80 (PDF p. 90).Weapon Systems Annual Assessment 2025 — LGM-35A Sentinel, p. 80 U.S. Government Accountability Office · Jun 11, 2025$170.6BBY2025 $
- Annual RDT&E fundingR-1 PE0605238F Ground Based Strategic Deterrent EMD. Annual appropriation, not lifetime development. FY2026 includes listed reconciliation spend-plan funds; FY2027 is requested funding. Not a contract award or recurring hardware price.FY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2027 total request · PB2027$4.521B / yrNominal $; source budget basis
- CAPE program acquisition estimateSource-reported acquisition estimate for a reasonably modified program, including command/launch infrastructure. GAO in February 2026 says costs remain uncertain. Not lifetime operations cost or missile-only procurement.Sentinel Nunn-McCurdy review results, July 2024 U.S. Air Force · figure July 2024 restructuring review$140.9BSource-reported $ · dollar year not specified in release
Unit costs · 1
- Comparable unit priceNo comparable standalone unit price was established; package or contract totals are shown separately.Source not recordedNot established
Quantities · 2
- Operational missiles to replaceReplacement mission for 400 Minuteman III missiles and 450 silos; not a total production quantity, new order or Sentinel inventory.FY2027 Budget Request Overview, nuclear modernization and missile warning DoD Comptroller · figure FY2027 overview400U.S. only; stated source scope
- U.S. inventoryA current U.S. inventory was not established. Annual procurement, cumulative deliveries and production capacity are not a stockpile count.Source not recordedNot established
Operating costs · 1
- Annual operations & supportA complete, system-specific annual operating and support cost was not established. Procurement, replacement rounds and contract support are different measures.Source not recordedNot established
Earlier observations · 4
Superseded estimates and prices, each in its original scope and dollar basis.
| Measure | Amount | Source |
|---|---|---|
| Annual RDT&E funding1 | $1.942B / yrNominal $; source budget basis | FY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2025 actual · PB2027 |
| Annual RDT&E funding1 | $4.805B / yrNominal $; source budget basis | FY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2026 total enacted / spend plan · PB2027 |
| Annual RDT&E funding1 | $4.521B / yrNominal $; source budget basis | FY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2027 total request · PB2027 |
| Development contract awardDistinct from the later total acquisition estimate; do not add award value to the acquisition total. | $13.3BNominal $; source budget basis | Sentinel engineering and manufacturing development award, September 8, 2020 U.S. Air Force · figure Sep 8, 2020 |
- Annual RDT&E funding1FY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2025 actual · PB2027$1.942B / yrNominal $; source budget basis
- Annual RDT&E funding1FY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2026 total enacted / spend plan · PB2027$4.805B / yrNominal $; source budget basis
- Annual RDT&E funding1FY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2027 total request · PB2027$4.521B / yrNominal $; source budget basis
- Development contract awardDistinct from the later total acquisition estimate; do not add award value to the acquisition total.Sentinel engineering and manufacturing development award, September 8, 2020 U.S. Air Force · figure Sep 8, 2020$13.3BNominal $; source budget basis
1R-1 PE0605238F Ground Based Strategic Deterrent EMD. Annual appropriation, not lifetime development. FY2026 includes listed reconciliation spend-plan funds; FY2027 is requested funding. Not a contract award or recurring hardware price.
Most cost growth sits outside the missile body
The 2024 review identifies the command-and-launch segment as the main source of cost growth. A program total divided by 400 operational replacements would allocate infrastructure and other development as if it were missile hardware. GAO’s February 2026 review still describes a restructuring program with uncertain costs.
Warhead and reentry-vehicle spending is separate
The Air Force procurement book lists the Mk21A reentry vehicle separately from Sentinel and identifies its interface with the NNSA W87-1 program. Neither is silently added to the Sentinel missile price.
Contracts & purchasing · 1
Ceilings, options and purchase agreements are not spending and are never added together. Obligations are under Contracts.
| Buyer → seller | Status | Stated amount | Qty | Source |
|---|---|---|---|---|
| U.S. Air Force → Northrop GrummanDevelopment contract; not lifetime program R&D or purchase of a fielded missile fleet. | Engineering and manufacturing development award | $13.3B | — | Sentinel engineering and manufacturing development award, September 8, 2020 U.S. Air Force · figure Sep 8, 2020 |
International buyers · 1
| Country | Qty | Status | Source |
|---|---|---|---|
| United StatesNo foreign purchase is established; operational replacement requirements are not deliveries. | Not verified | Air Force development customer | Sentinel engineering and manufacturing development award, September 8, 2020 U.S. Air Force · figure 2020 award / FY2027 request |
Open research: Current U.S. inventory and complete annual operating-and-support costs require additional public evidence. Buyer records are selected examples, not a complete global order book.
What the government budgets and pays for this program, from budget justification books, appropriations, acquisition reports and contract announcements. Each figure states its dollar basis. What contractors were obligated is under Contracts.
Contracts$13.75B obligated on code-mapped awards
- Code-mapped awards are every contract award in the USAspending baseline (DoD, DHS, DOE and NASA, FY2008–FY2027) whose latest reported acquisition program code is this program's, whichever company received it; vehicles (IDVs) are excluded.
By fiscal year9
| Fiscal year | Obligated | Actions |
|---|---|---|
| FY2018 | $8.0M obligated | 4 |
| FY2019 | $1.9M obligated | 9 |
| FY2020 | $117M obligated | 6 |
| FY2021 | $1.09B obligated | 12 |
| FY2022 | $2.03B obligated | 17 |
| FY2023 | $2.87B obligated | 8 |
| FY2024 | $3.49B obligated | 15 |
| FY2025 | $1.28B obligated | 15 |
| FY2026 | $2.86B obligated | 11 |
Contractors5
- Northrop Grumman$13.72B obligated 100%
- Booz Allen Hamilton$14.9M obligated 0.1%
- Dark Wolf Solutions$7.1M obligated 0.1%
- Sterling Computers Corporation$4.2M obligated 0.0%
- AKIRA TECHNOLOGIES INC.$38K obligated 0.0%
- Recipients without a DefDex profile (2 awards)$5.6M obligated 0.0%
Reported acquisition program code 493; program scope may be incomplete or miscoded · 7 awards. Obligations are signed USAspending prime-contract actions on the awards counted here, negative and zero actions included, credited to each award's company. Obligations are money committed, not company revenue or total program spending. How DefDex totals programs.
Participants8
Prime
1- Northrop Grumman Systems CorporationConfirmed

In July 2026 Northrop Grumman broke ground on a new building at its Roy Innovation Center in Utah, the central campus built to develop the Air Force's Sentinel ICBM, with nearly 5,000 Northrop Grumman employees working across the country on the program.
Source: news.northropgrumman.com
Teammate
6Clark Construction is on the Sentinel team.
Source: www.bechtel.com
Honeywell is on the Sentinel team.
Source: www.bechtel.com
Kratos Defense and Security Solutions is on the Sentinel team.
Source: www.bechtel.com
L3Harris is on the Sentinel team.
Source: www.bechtel.com
Lockheed Martin is on the Sentinel team.
Source: www.bechtel.com
Textron Systems is on the Sentinel team.
Source: www.bechtel.com
Subcontractor
1Bechtel is working with its customer Northrop Grumman to help design and construct the launch infrastructure component of Sentinel.
Source: www.bechtel.com
Roles as recorded: a prime holds the contract, teammates and subcontractors build under it, competing bidders bid against it, operators field the result.
Where It Is Built2
| Site | Role | Location | Work | Source | Confidence |
|---|---|---|---|---|---|
| Roy Innovation CenterNorthrop Grumman | Development | Office · Roy, Utah | In July 2026 Northrop Grumman described its existing Roy Innovation Center as a Sentinel development campus; the planned Legacy Building would expand it to six buildings and over 1.1 million square feet of office space. | news.northropgrumman.com news.northropgrumman.com | — |
| Roy Innovation Center Legacy BuildingNorthrop Grumman | Development | Office · Roy, Utah | Construction of Northrop Grumman's new Legacy Building at the Roy Innovation Center begins in summer 2026 and is to be completed by 2028. | news.northropgrumman.com news.northropgrumman.com | — |
- Development
- Development
Plants, shipyards, final-assembly lines, test sites and depots that build or sustain the program, and the work done at each.
Who Operates It1
| Country | Service | Relationship | Quantity | Note | Source | Confidence |
|---|---|---|---|---|---|---|
| United States | Air Force | Planned operator | 634 units planned | The Air Force plans to procure 634 Sentinel missiles, plus 25 to support development and testing, to enable deployment of 400 missiles. | www.congress.gov www.congress.gov | — |
- United StatesPlanned operator
Countries and services that operate or have bought the product. A quantity is the count a source states, labelled delivered, in service, ordered, planned or authorized with the year it is stated for; an ordered, planned or authorized count is not a delivery.