Cost to the Government
| Measure | Variant | Amount | Source |
|---|---|---|---|
| Program totals · 3 | |||
| Gross procurement request373 weapons plus containers, testing, support and obsolescence. Broader scope than recurring AUR hardware. | Air Force | $194.509MNominal $; source budget basis | FY2027 Missile Procurement, Air Force: discretionary and mandatory requests U.S. Air Force · Apr 2026 · figure FY2027 |
| SDB annual RDT&E referenceR-1 PE0207327F Small Diameter Bomb. Annual appropriation, not lifetime development. FY2026 includes listed reconciliation spend-plan funds; FY2027 is requested funding. Shared scope; cannot be attributed solely to this product. | Air Force | $25.497M / yrNominal $; source budget basis | FY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2027 total request · PB2027 |
| R&D program totalA lifetime program R&D total was not established. Development contracts and shared program budgets are not substituted for that total. | All | Not established | — |
| Unit costs · 1 | |||
| All-up round / weaponSDB002 P-5 recurring AUR estimate, rounded to thousands. Separate weapon containers and support excluded. FY2025 quantity has an internal correction note, so no FY2025 per-unit value is derived from totals. | Air Force | $274,000Nominal $ · source budget basis | FY2027 Missile Procurement, Air Force: discretionary and mandatory requests U.S. Air Force · Apr 2026 · figure FY2027 request |
| Quantities · 2 | |||
| Requested weaponsAir Force only; excludes separate Navy procurement. Not inventory. | Air Force | 373U.S. only; stated source scope | Air Force posture hearing: B-52 modernization and LRSO integration U.S. Congress · figure FY2027 |
| U.S. inventoryA current U.S. inventory was not established. Annual procurement, cumulative deliveries and production capacity are not a stockpile count. | All | Not established | — |
| Operating costs · 1 | |||
| Annual operations & supportA complete, system-specific annual operating and support cost was not established. Procurement, replacement rounds and contract support are different measures. | All | Not established | — |
Program totals · 3
- Gross procurement request373 weapons plus containers, testing, support and obsolescence. Broader scope than recurring AUR hardware.Air ForceFY2027 Missile Procurement, Air Force: discretionary and mandatory requests U.S. Air Force · Apr 2026 · figure FY2027$194.509MNominal $; source budget basis
- SDB annual RDT&E referenceR-1 PE0207327F Small Diameter Bomb. Annual appropriation, not lifetime development. FY2026 includes listed reconciliation spend-plan funds; FY2027 is requested funding. Shared scope; cannot be attributed solely to this product.Air ForceFY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2027 total request · PB2027$25.497M / yrNominal $; source budget basis
- R&D program totalA lifetime program R&D total was not established. Development contracts and shared program budgets are not substituted for that total.Source not recordedNot established
Unit costs · 1
- All-up round / weaponSDB002 P-5 recurring AUR estimate, rounded to thousands. Separate weapon containers and support excluded. FY2025 quantity has an internal correction note, so no FY2025 per-unit value is derived from totals.Air ForceFY2027 Missile Procurement, Air Force: discretionary and mandatory requests U.S. Air Force · Apr 2026 · figure FY2027 request$274,000Nominal $ · source budget basis
Quantities · 2
- Requested weaponsAir Force only; excludes separate Navy procurement. Not inventory.Air ForceAir Force posture hearing: B-52 modernization and LRSO integration U.S. Congress · figure FY2027373U.S. only; stated source scope
- U.S. inventoryA current U.S. inventory was not established. Annual procurement, cumulative deliveries and production capacity are not a stockpile count.Source not recordedNot established
Operating costs · 1
- Annual operations & supportA complete, system-specific annual operating and support cost was not established. Procurement, replacement rounds and contract support are different measures.Source not recordedNot established
Earlier observations · 6
Superseded estimates and prices, each in its original scope and dollar basis.
| Measure | Amount | Source |
|---|---|---|
| Program totals · 3 | ||
| SDB annual RDT&E reference1 | $29.047M / yrNominal $; source budget basis | FY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2025 actual · PB2027 |
| SDB annual RDT&E reference1 | $24.575M / yrNominal $; source budget basis | FY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2026 total enacted / spend plan · PB2027 |
| SDB annual RDT&E reference1 | $25.497M / yrNominal $; source budget basis | FY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2027 total request · PB2027 |
| Unit costs · 3 | ||
| All-up round / weapon2 | $239,000Nominal $ · source budget basis | FY2027 Missile Procurement, Air Force: discretionary and mandatory requests U.S. Air Force · Apr 2026 · figure FY2025 · PB2027 |
| All-up round / weapon2 | $265,000Nominal $ · source budget basis | FY2027 Missile Procurement, Air Force: discretionary and mandatory requests U.S. Air Force · Apr 2026 · figure FY2026 · PB2027 |
| All-up round / weapon2 | $274,000Nominal $ · source budget basis | FY2027 Missile Procurement, Air Force: discretionary and mandatory requests U.S. Air Force · Apr 2026 · figure FY2027 request |
Program totals · 3
- SDB annual RDT&E reference1FY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2025 actual · PB2027$29.047M / yrNominal $; source budget basis
- SDB annual RDT&E reference1FY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2026 total enacted / spend plan · PB2027$24.575M / yrNominal $; source budget basis
- SDB annual RDT&E reference1FY2027 R-1: Research, Development, Test & Evaluation Department of Defense Comptroller · Apr 2026 · figure FY2027 total request · PB2027$25.497M / yrNominal $; source budget basis
Unit costs · 3
- All-up round / weapon2FY2027 Missile Procurement, Air Force: discretionary and mandatory requests U.S. Air Force · Apr 2026 · figure FY2025 · PB2027$239,000Nominal $ · source budget basis
- All-up round / weapon2FY2027 Missile Procurement, Air Force: discretionary and mandatory requests U.S. Air Force · Apr 2026 · figure FY2026 · PB2027$265,000Nominal $ · source budget basis
- All-up round / weapon2FY2027 Missile Procurement, Air Force: discretionary and mandatory requests U.S. Air Force · Apr 2026 · figure FY2027 request$274,000Nominal $ · source budget basis
1R-1 PE0207327F Small Diameter Bomb. Annual appropriation, not lifetime development. FY2026 includes listed reconciliation spend-plan funds; FY2027 is requested funding. Shared scope; cannot be attributed solely to this product.
2SDB002 P-5 recurring AUR estimate, rounded to thousands. Separate weapon containers and support excluded. FY2025 quantity has an internal correction note, so no FY2025 per-unit value is derived from totals.
Falling quantities can raise the program average
The FY2027 budget requests 373 Air Force weapons and retains support and obsolescence costs. Its gross program average is substantially broader than the $274,000 recurring weapon estimate.
Contracts & purchasing · 2
Ceilings, options and purchase agreements are not spending and are never added together. Obligations are under Contracts.
| Buyer → seller | Status | Value | Qty | Source |
|---|---|---|---|---|
| U.S. Air Force → RaytheonSource states more than 1,500 weapons; an exact quantity is not supplied and the contract is not divided by 1,500 to claim a precise unit price. | Production award announced | $345M | — | StormBreaker production award, January 3, 2024 RTX / Raytheon · figure Jan 3, 2024 |
| Norway → U.S. Foreign Military Sales600 total SDB II rounds in the revised case, including 20 in the earlier below-threshold case plus 580 added. Includes support; not a confirmed delivered order. | Proposed sale · congressional notification | $293M | 600 | Norway SDB II proposed sale, notification 23-41, Congressional Record July 10, 2023 Congressional Record / DSCA · figure Jun 28, 2023 |
International buyers · 1
| Country | Qty | Status | Source |
|---|---|---|---|
| NorwayTotal includes 20 previously covered rounds; do not add 600 and 20. Delivery not established. | 600 | Revised proposed sale scope | Norway SDB II proposed sale, notification 23-41, Congressional Record July 10, 2023 Congressional Record / DSCA · figure Jun 28, 2023 |
Open research: Current U.S. inventory and complete annual operating-and-support costs require additional public evidence. Buyer records are selected examples, not a complete global order book.
What the government budgets and pays for this program, from budget justification books, appropriations, acquisition reports and contract announcements. Each figure states its dollar basis. What contractors were obligated is under Contracts.
Contracts$3.79B obligated since FY2008
Awards50
- RTXJETTISON TEST VEHICLE X (JTV-X)U.S. Air Force · Delivery Order · Jul 8, 2026$4.1Mobligated · up to $4.1M ceiling
- RTXSDB II LOT 12/TE UCAU.S. Air Force · Definitive Contract · Apr 6, 2026$339Mobligated · up to $357M ceiling
- RTXTHE PURPOSE OF THIS EFFORT IS TO PROVIDE SUPPORT TO THE USAF, DON, AND FOREIGN MILITARY SALES (FMS) SDB II/GBU-53 PROGRAM FOR NON-WARRANTY REPAIRS, LOGISTICS SUPPORT AND SPARES MANAGEMENT.U.S. Air Force · Delivery Order · Sep 24, 2025$3.1Mobligated · up to $6.3M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT II - TECHNOLOGY REFRESH PHASE 3U.S. Air Force · Delivery Order · Aug 13, 2025$53.8Mobligated · up to $53.8M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT IIU.S. Air Force · Delivery Order · Jul 3, 2025$4.1Mobligated · up to $5.1M ceiling
- RTXSIP 25+U.S. Air Force · Delivery Order · Apr 30, 2025$37.2Mobligated · up to $58.3M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT II PRODUCTION LOT 11U.S. Air Force · Definitive Contract · Dec 19, 2024$367Mobligated · up to $368M ceiling
- RTXENGINEERING SERVICES 4U.S. Air Force · Delivery Order · May 24, 2024$2.9Mobligated · up to $3.2M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT IIU.S. Air Force · Delivery Order · Jan 30, 2024$2.9Mobligated · up to $2.9M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT IIU.S. Air Force · Delivery Order · Apr 3, 2023$2.9Mobligated · up to $3.2M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT IIU.S. Air Force · Delivery Order · Mar 30, 2023$4.1Mobligated · up to $4.5M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT IIU.S. Air Force · Definitive Contract · Mar 23, 2023$686Mobligated · up to $689M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT IIU.S. Air Force · Delivery Order · Feb 21, 2023$122Mobligated · up to $132M ceiling
- BoeingSMALL DIAMETER BOMB I EJECTOR HOUSING UNITSU.S. Air Force · Delivery Order · Jul 28, 2022$18.1Mobligated · up to $18.1M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT IIU.S. Air Force · Delivery Order · Apr 1, 2022$50.4Mobligated · up to $50.4M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT IIU.S. Air Force · Delivery Order · Mar 28, 2022$62.4Mobligated · up to $65.0M ceiling
- BoeingNAVY SYSTEM LEVEL ANALYSIS AND TECHNICAL SUPPORTU.S. Air Force · Delivery Order · Oct 3, 2021$2.5Mobligated · up to $5.9M ceiling
- RTXSMALL DIAMETER BOMB IIU.S. Air Force · Delivery Order · Jul 12, 2021$9.5Mobligated · up to $12.3M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT IIU.S. Air Force · Definitive Contract · Apr 29, 2021$436Mobligated · up to $612M ceiling
- RTXSMALL DIAMETER BOMB II LOT INTEGRATION & TESTU.S. Air Force · Delivery Order · Apr 4, 2021$132Mobligated · up to $144M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT II LOT 6 TEST EQUIPMENTU.S. Air Force · Delivery Order · Oct 20, 2020$17.5Mobligated · up to $19.6M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT IIU.S. Air Force · Definitive Contract · Apr 28, 2020$274Mobligated · up to $259M ceiling
- RTXSMALL DIAMETER BOMB II SYSTEM IMPROVEMENT PROGRAM (SIP) 2020U.S. Air Force · Delivery Order · Mar 19, 2020$19.4Mobligated · up to $28.7M ceiling
- RTXSMALL DIAMETER BOMB IIU.S. Air Force · Delivery Order · Sep 30, 2019$102Mobligated · up to $102M ceiling
- RTXSMALL DIAMETER BOMB IIU.S. Air Force · Delivery Order · Sep 30, 2019$3.9Mobligated · up to $3.5M ceiling
- RTXSMALL DIAMETER BOMB IIU.S. Air Force · Delivery Order · Sep 30, 2019$2.6Mobligated · up to $3.3M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT IIU.S. Air Force · Delivery Order · Jun 14, 2019$7.5Mobligated · up to $7.6M ceiling
- RTXSDB II&F/A-18 INTEGRATION, FLIGHT TEST SUPPORTU.S. Air Force · Delivery Order · May 22, 2019$11.8Mobligated · up to $12.1M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT IIU.S. Air Force · Delivery Order · Mar 20, 2019$3.7Mobligated · up to $3.7M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT II SPT F/A-18 INTEGRATION, HARDWAREU.S. Air Force · Delivery Order · Feb 25, 2019$2.7Mobligated · up to $3.2M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT IIU.S. Air Force · Definitive Contract · Dec 18, 2018$143Mobligated · up to $143M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT IIU.S. Air Force · Delivery Order · Oct 16, 2018$6.8Mobligated · up to $6.9M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT II, SOFTWARE MAINTENANCE 2018U.S. Air Force · Delivery Order · Aug 20, 2018$27.8Mobligated · up to $28.0M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT II SPT INTEGRATION/FLIGHT TESTU.S. Air Force · Delivery Order · Jun 28, 2018$5.4Mobligated · up to $5.4M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT IIU.S. Air Force · Delivery Order · May 18, 2018$14.3Mobligated · up to $4.6M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT IIU.S. Air Force · Definitive Contract · Feb 27, 2018$88.7Mobligated · up to $88.7M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT II - M-CODE DESIGN&INTU.S. Air Force · Delivery Order · Jan 4, 2018$416Mobligated · up to $420M ceiling
- BoeingLASER SMALL DIAMETER BOMB (LSDB)U.S. Air Force · Delivery Order · Dec 7, 2017$10.2Mobligated · up to $8.9M ceiling
- RTXSMALL DIAMETER BOMB IIU.S. Air Force · Delivery Order · Aug 15, 2017$8.1Mobligated · up to $3.0M ceiling
- RTXIGF::CT::IGF SMALL DIAMETER BOMB II, SOFTWARE MAINTENANCE 2017U.S. Air Force · Delivery Order · Jul 31, 2017$10.5Mobligated · up to $13.9M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT II - JMM BRU FOLLOW ON SUPPORTU.S. Air Force · Delivery Order · Jul 25, 2017$10.0Mobligated · up to $10.0M ceiling
- RTXSMALL DIAMETER BOMB II - LOT 3 PRODUCTIONU.S. Air Force · Definitive Contract · Jan 27, 2017$72.4Mobligated · up to $63K ceiling
- RTXSMALL DIAMETER BOMB INCREMENT II - CRYPTOGRAPHIC MODERNIZATION BRIDGE STUDYU.S. Air Force · Delivery Order · Dec 7, 2016$3.8Mobligated · up to $3.9M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT II LOT 2 PRODUCTIONU.S. Air Force · Definitive Contract · Sep 8, 2016$57.3Mobligated · up to $49.3M ceiling
- RTXSMALL DIAMETER BOMB II - MILITARY CODE, GLOBAL POSITIONING SYSTEM (GPS) RECEIVER PHASE IU.S. Air Force · Delivery Order · Sep 1, 2016$3.5Mobligated · up to $3.7M ceiling
- RTXSMALL DIAMETER BOMB INCREMENT II (SDB II)U.S. Air Force · Delivery Order · Jun 22, 2016$6.1Mobligated · up to $6.1M ceiling
- RTXSMALL DIAMETER BOMB II LOT 1Defense Contract Management Agency · Definitive Contract · Jun 12, 2015$66.0Mobligated · up to $712M ceiling
- RTXSMALL DIAMETER BOMB II - F/A-18E/F AIRCRAFT INTEGRATION TEST ASSETSU.S. Air Force · Definitive Contract · Jun 8, 2015$8.5Mobligated · up to $4.7M ceiling
- RTXJOINT MINIATURE MUNITIONS BOMB RACK UNIT (JMM BRU) IDIQ - FILTER LIFE CALCULATION CAPABILITYU.S. Air Force · Delivery Order · Jun 5, 2015$2.8Mobligated · up to $2.5M ceiling
- RTXJOINT MINIATURE MUNITIONS BOMB RACK UNIT (JMM BRU) - F/A-18 H/W IMVSU.S. Air Force · Delivery Order · Jun 4, 2015$5.7Mobligated
Obligations are signed USAspending prime-contract actions coded to this program, FY2008 to date, credited to the company that received each action. Obligations are money committed, not company revenue.